To update a task there are two options. You can scroll through the list of tasks and find the task you want to update or you can search for it. Once you find the task you’re looking for simply select it and then slide the Task Progress icon to the desired percentage.

Signing into onTarget with Procore Credentials


Go to https://platform.ontargetcloud.com/#/signin

ontarget_-_hollister_training_640_02

 

Signing into onTarget with Procore Credentials

Part 1:

procore_log_in_2_640_01

 

Part 2:

ontarget_-_hollister_training_2_640_01

 

Viewing Entire Schedule Sorted by Task ID#

1st Click on the “Filter By” and then click “All Dates”

2nd Click descending arrow

 

 

ontarget_-_hollister_training_2_1_1_640_01 

 

Filter by 2 Week Look Ahead

1st Click on the “Filter By” and then click “2 Weeks”

 

ontarget_-_hollister_training_2_2_640_01

 

Create Parent & Child Task

 

ontarget_-_hollister_training_2_3_640_01

 

Updating a Tasks Progress Percentage

1st option is to type directly into the “Progress” Column. If the “Progress” column is not showing hover your mouse over any of the column headers such as “Title” and right-click. This will bring up a pop-up menu and from here you can selected additional columns.

 

ontarget_-_hollister_training_2_4_1_640_01

 

The second option to update a tasks progress and to view more details is Double -Clicking on the task from the main gantt schedule viewer. Once the detail task window appears there many functions you can perform.

 

ontarget_-_hollister_training_640_03

 

Assign Task

 

ontarget_-_hollister_training_2_7_640_01

 

 